Archaeological Services in Zala County
The protection and preservation of Hungary’s cultural heritage are governed by Act LXIV of 2001 on the Protection of Cultural Heritage and Government Decree 68/2018 (IV. 9.) on the protection of cultural heritage. Following the conclusion of a prior agreement, the required archaeological services within Zala County are provided by the Balaton Museum, the Thúry György Museum, and the Zalaegerszeg Museums Directorate. According to the Cultural Heritage Act, the costs of archaeological work must be covered by the party whose planned earthworks require the disturbance of an archaeological site.
Fees for Archaeological Services
The fees for archaeological services are determined by legislation. The applicable charges are set out in Annex 8 of Government Decree 68/2018 (IV. 9.). You can find the current fee schedule here.
Priority Major Investment Projects
For priority major investment projects, the developer is required to obtain a Preliminary Archaeological Documentation (PAD) before a building permit can be issued. The PAD assesses the archaeological significance of the planned development area. Information about the preparation of the Preliminary Archaeological Documentation (PAD) is available here. The developer must conclude an agreement with the Hungarian National Museum for the preparation of the PAD and, where required by the building permit, for any preventive excavation or archaeological monitoring.
Major Investment Projects
For major investment projects, the developer must obtain a Preliminary Archaeological Documentation (PAD) before a building permit can be issued. Based on the PAD, if the building permit or other official decision requires preventive archaeological excavation or archaeological monitoring, the developer must conclude an agreement with the Zalaegerszeg Museums Directorate. To prepare the agreement, please complete the required information on this form and submit it electronically to zalaregeszet@zmmi.hu.
Standard Development Projects
Most developments affecting archaeological sites fall into the category of standard development projects. If the building permit or official decision issued by the competent authority requires full-scale archaeological excavation or archaeological monitoring, the developer must conclude an agreement with the Zalaegerszeg Museums Directorate. To prepare the agreement, please complete the required information on this form and submit it electronically to zalaregeszet@zmmi.hu.
Glossary of Archaeological Terms
Archaeological Monitoring
Archaeological monitoring is required when:
- the planned activity does not affect, or only minimally affects, a registered archaeological site or archaeological remains;
- archaeological remains are expected to occur only sporadically;
- the planned earthworks do not reach the depth at which archaeological remains are expected to occur;
- the affected part of a registered archaeological site has previously been disturbed by earthworks, or when the technical characteristics of the project make other forms of archaeological work impractical. In such cases, archaeological monitoring is prescribed.
The purpose of archaeological monitoring is for an archaeologist to continuously observe the earthworks on site and, where necessary, carry out and document archaeological excavation.
If archaeological monitoring is required by the building permit, the developer must contact the competent regional museum (in this case, the Zalaegerszeg Museums Directorate), where they will be informed which archaeologist will be responsible for carrying out the monitoring.
Trial Excavation
The purpose of a trial excavation is to determine the extent and intensity of an archaeological site. This makes it possible to establish whether preventive excavation is necessary and, if so, to estimate the time and costs involved. A developer may request a trial excavation before purchasing a property or during the planning phase, which can greatly assist in scheduling and budgeting the project.
A trial excavation begins with the excavation of test trenches using both mechanical and manual methods. To determine whether further archaeological work will be required, the total area of the trenches must cover at least 10% of the development site, which may be increased to a maximum of 25%. Following the excavation, the archaeologist prepares a professional report for both the developer and the competent authority. Based on this report, the authority decides whether preventive excavation, archaeological monitoring, or no further archaeological work is required.
Full Preventive Excavation
A preventive excavation is required when a planned development would certainly damage, endanger, or destroy an archaeological site. The excavation covers the entire area affected by the planned earthworks. Depending on the nature of the archaeological site, excavation may be limited to the planned construction depth or extend through the full depth of the archaeological layers. The work is carried out using both mechanical equipment and manual excavation. The duration and schedule of the excavation are determined by the terms of the contract.